Winterization
With the floor of the building now in place, the floor and foundation have been covered to protect them from weather during the upcoming winter.
Vintage Diesels
With the floor of the building now in place, the floor and foundation have been covered to protect them from weather during the upcoming winter.
Our contractor poured the concrete floor for the building on November 24, 2021. To prevent winter damage, the concrete block wall was filled with concrete. With those tasks done, the … Read more
The Benz engine is nearing completion, and a test run. It will be mounted on its foundation in the Spring
Finally we have decided upon a name for our project. We have chosen this name and logo for our building in honor of the great vintage Diesel Centrale plant in … Read more
All the floor hydronic heating tubes have been placed and tested. The concrete floor will soon be poured.